NEW QUESTION # 28
When is a Timebox Plan updated?
- A. At Timebox Kick-ups
- B. Each time a Timebox is completed
- C. At the Daily Start-ups
- D. As needed by the Project Manager
Answer: B
NEW QUESTION # 29
Which of the following are recognized DSDM styles of Timebox?
1. Unstructured
2. Consolidated
- A. Both 1 and 2 are true
- B. Only 1 is true
- C. Only 2 is true
- D. Neither 1 or 2 is true
Answer: A
NEW QUESTION # 30
According to the DSDM principle 'Never Compromise Quality, when should the overall level of quality to be delivered within the solution be agreed?
- A. At the start of the project
- B. During evolutionary development
- C. When the Business Advisor is available
- D. Whenever the level of solution quality is known.
Answer: B
NEW QUESTION # 31
How should DSDM team measure progress?
- A. Based on what has been delivered at the end of a Timebox.
- B. Based on the completion of activities rather than the delivery of products
- C. Through a project dashboard
- D. Through an analysis of the Instrumental Success Factors.
Answer: A
NEW QUESTION # 32
Identify the missing word in the following sentence.
The Business Sponsor is known as the project [?] because they are committed to the solution and the delivery approach.
- A. director
- B. Visionary
- C. Champion
- D. Governor
Answer: B
NEW QUESTION # 33
Which technique allows for testing the achievailability of objectives?
- A. Timeboxing
- B. MoSCoW
- C. Modeling
- D. Facilitated Workshop
Answer: D
NEW QUESTION # 34
Which information is given in the Solution Architecture Definition?
- A. A high-level design framework for the solution.
- B. The strategy for testing
- C. A snapshot of the evolving business, solution and management products
- D. The tools and standards to be used in Evolutionary Development
Answer: C
NEW QUESTION # 35
What phase will create Solution increments?
- A. Deployment
- B. Feasibility
- C. Evolutionary Development
- D. Foundations
Answer: C
NEW QUESTION # 36
Which of the following is a DSMD principle?
- A. Build incrementally
- B. Build incrementally from firm foundations
- C. Build incrementally from Feasibility onwards
- D. Build incrementally in Timeboxes
Answer: B
NEW QUESTION # 37
How is Quality ensured during Evolutionary Development?
- A. By understanding and managing priorities
- B. By continuous verification
- C. By facilitating session to enable a group to work to achieve an agreed goal
- D. By managing objectives in a fixed time period
Answer: C
NEW QUESTION # 38
What is the MoSCoW technical used for?
- A. Understanding and managing priorities.
- B. As an opportunity to share information across the team and to do any day.to.day re-planning and reorganizing as necessary when issues occur.
- C. Creating a visual representation of a problem or a solution.
- D. Ensuring a team-based approach through visual and verbal communication and collaboration.
Answer: A
NEW QUESTION # 39
Which phase in the DSDM process aims to understand the scope of work and, in broad terms, how it will carried out, by whom, when and where?
- A. Evolutionary Development
- B. Feasibility
- C. Foundations
- D. Pre-Project
Answer: C
NEW QUESTION # 40
During what phase should a baseline of the Evolving Solution be put into operational use?
- A. Deployment
- B. Post-Project
- C. Evolutionary Development
- D. Foundations
Answer: A
NEW QUESTION # 41
What role is responsible for interpreting the needs of the Business Sponsor and communicating these to the team?
- A. Technical Coordinator
- B. Team Leader
- C. Business Visionary
- D. Business Analyst
Answer: C
NEW QUESTION # 42
Identify the missing words in the following sentence.
Principles 1 -Focus on the Business Need suggests that every decision taken during a project should be [?] - to deliver what the business needs to be delivered.
- A. The responsibility of the Business Sponsor
- B. Viewed in light of the overriding project goal
- C. Made collaboratively
- D. Share between all of the project roles
Answer: C
NEW QUESTION # 43
Which plain defined by DSDM, has a planning horizon that includes the end of a project?
- A. Delivery
- B. Timebox
- C. Detailed
- D. High-Level
Answer: A
NEW QUESTION # 44
How is contingency typically managed in a DSDM project?
- A. Managed by varying the features to be delivered.
- B. Allowed adding a percentage to the high-level estimates.
- C. Managed by varying time and cost
- D. Not needed in a DSDM project.
Answer: A
NEW QUESTION # 45
What role, ideally, should be independent of the outcome to be achieved in a Facilitated Wordshop?
- A. Workshop Facilitator
- B. Business Ambassador
- C. Business Visionary
- D. Business Analyst
Answer: A
NEW QUESTION # 46
......
The AgilePM-Foundation Certification Exam is administered by APMG-International, a global accreditation and certification body that offers a wide range of certifications in project management, IT service management, and cybersecurity. APMG-International is known for its high-quality certification exams and rigorous standards. The AgilePM-Foundation Certification Exam is one of the most popular certifications offered by APMG-International, and it is recognized by many organizations worldwide. Candidates who pass the AgilePM-Foundation Certification Exam will have a valuable credential that can help them advance their careers in project management.